Construction Cost Estimating

The figures below are provided for your convenience.  Of course, cost considerations are never as simple as comparing product A to product B.  Installed cost and operating cost must be considered as well as unit price.  These costs are all affected by project size, location, labor market, current freight rates, building codes, and the particular application.

     Unit Cost
     Installed Cost
     Operating Cost
     Rough Estimator
     Job Takeoff

Unit Cost:

Unit prices for SafeCrete autoclaved aerated concrete construction products can be found on our
Products page.  Most products are purchased in full pallet increments.

Installed Cost:

When comparing installed cost of AAC to other building construction methods, please take into account that AAC typically replaces:

  • Wood or metal studs
  • Insulation
  • OSB
  • Exterior Sheathing
  • Interior Sheathing (when choosing plaster over sheetrock)
  • Fancy window trim, ledges, quoins, and other exterior decoration
  • Fire-rated walls

    SafeCrete AAC construction supply may also reduce the size and cost of:
  • Foundation
  • A/C units 

    The following is an installed construction cost estimate for a sample customer.  Individual job costs will vary. Please note that labor costs may vary considerably from one location to another.

    Item Cost Notes:
     8-inch exterior walls  $2.58 per square foot  Does not includes lintels
     6-inch interior walls  $1.94 per square foot  Non-loadbearing
     Thin-set Mortar  $0.19 per square foot  
     Block installation  $3.00 per square foot  
     Exterior Stucco  $3.75 per square foot  Includes materials & labor
     Interior Stucco  $1.85 per square foot  Includes materials & labor
    Totals
     Exterior Walls Installed Cost $11.37 per square foot  Both sides finished
     Interior Walls Installed Cost $  8.83 per square foot  Both sides finished

    Operating Cost:

    To the owner of a green building, monthly operating cost is a greater factor than actual construction cost.

    Monthly Savings:
  • Considerable savings on heating and cooling
  • Reduced insurance rates Contact us!">

    Select Block Type to Estimate Construction Cost:
    Standard Block U-Block
    Floor and Roof Panels

    Job Takeoff:

    Please contact us to discuss your green building project.  We can suggest ways to reduce installed cost and operating cost, as well as providing a material estimate and freight rates.  Please send us your blueprints.   

    Ready to build your sustainable home?